Does Your Renovation Need a BC Land Surveyor? A Lower Mainland Guide
Updated: Oct 29

You're planning an addition, raising the house, or changing the grades out back, and someone tells you you'll need a survey. Do you? Sometimes yes, sometimes no. It depends on the work, the municipality, and sometimes on what the building official asks for. Here's a plain look at when a survey comes up, what it is, and where Archivolt fits in.
Requirements vary by municipality; confirm with yours.
First: how Archivolt helps with surveys
Archivolt is a permits and drafting company. Legal and topographic surveys, property lines and certifying where a building sits on a lot are the work of a BC Land Surveyor. Under the Land Surveyors Act, only a practising land surveyor (or an authorized land surveying company) can establish boundaries, certify a feature's location relative to a boundary, prepare boundary plans or give boundary advice.
What we do: check what your municipality's permit checklist asks for, tell you whether a survey is likely to come up, coordinate with your surveyor, and use the sealed survey as the base for site plans, height and setback checks, and permit drawings. We also measure buildings for as-built drawings. Where a checklist calls for a survey, it's the sealed survey from a BC Land Surveyor that the municipality looks for.
What a survey actually is
When a permit checklist asks for a "topographical survey" or "site survey", it usually means a plan signed and sealed by a BC Land Surveyor that shows things like:
property lines and pins
existing buildings
grades (ground elevations), often at the corners of the lot and the building
trees, retaining walls, and registered easements and rights-of-way
datum points, and sometimes elevations on the street, lane or the neighbour's side
Exactly what has to be shown depends on the municipality's checklist. Some ask for tree details, some for grades on neighbouring land, some for datum at the property corners.
People also use terms like "building location certificate", "foundation survey" and "forms survey". These aren't all the same thing, and there's no single official BC definition that covers them, so ask your surveyor and your municipality which one they mean.
By-law, checklist, or the building official's call
It helps to keep three things apart:
What a by-law requires. For example, the Vancouver Building By-law has a section on up-to-date surveys.
What a permit checklist asks for. Checklists are the municipality's list of what to submit with a given type of application. They change more often than by-laws.
What the building official decides. In some cases, a survey is only needed if the building official asks for it.
A fourth category is just good practice: cases where no rule asks for a survey, but having one saves you from a redesign later.
When a survey often comes up
These are the usual triggers we see in municipal requirements:
Additions. Adding floor area on the outside usually means setbacks, coverage and height get checked against surveyed lines and grades.
Raising the house or rebuilding the foundation.
Changing grades or building retaining walls. Height and grade checks rely on surveyed existing grades.
New houses, duplexes and infill or laneway-type homes.
Work near an easement or right-of-way.
A design close to a height, setback or coverage limit. This one is good practice more than a rule. If you're within a few centimetres of a limit, you want real numbers.
Interior-only work often doesn't need a survey. Not every renovation does.
What some Lower Mainland municipalities say
These are from the municipalities' own documents. Checklists get revised, so confirm the current version before you apply.
Vancouver. The Vancouver Building By-law says a survey certified by a registered land surveyor no more than six months before it's delivered is required for all new buildings once the foundations and footings are done, before further construction. For an existing building, it's required if the Chief Building Official asks for it, to confirm the building's location and size or its relationship to neighbouring grades. Separately, the City of Vancouver's addition and renovation checklist (2022) says a survey plan is "required for most renovation projects including, but not limited to: addition, raising the building, re-constructing the foundation, and/or altering grades." Some Vancouver checklists use a different survey age than the by-law, so confirm with the City which applies to your application.
Burnaby. Burnaby's submission checklist for additions and alterations to existing single and duplex dwellings in the R1 zone lists a topographical survey or posting plan, signed and sealed and not more than 12 months old, marked "if applicable". The checklist doesn't spell out when it applies, so confirm with Burnaby for your project.
District of North Vancouver. The District's interior renovation and secondary suite checklist asks for a topographical survey by a registered BC Land Surveyor, signed, sealed and issued within the last six months, "if the value of work exceeds $200k or the scope of work is in the District ROW." That's a permit-checklist item. The District's permit questionnaire also lists survey items for major additions and alterations, new houses, demolition, retaining walls over 3 ft and in-ground pools.
City of North Vancouver. This is a separate municipality from the District, with its own rules. Its checklist for single and two-family additions asks for a current survey or posting plan by a BC Land Surveyor and says surveys older than six months "may not be acceptable."
West Vancouver. The single family and duplex permit checklist (which covers additions and alterations) asks for a topographical survey by a registered BC Land Surveyor, sealed within six months of the application date, including trees with size and species. It says interpolated grades and sealed site plans won't be accepted in its place.
Surrey. Surrey's checklist for new single-family and duplex homes lists a topographical survey, signed and sealed by a registered BC Land Surveyor and no older than six months. That checklist is for new homes. For an addition or renovation in Surrey, confirm with the municipality what it wants.
For other municipalities, check that municipality's current checklist or ask us to look into it.
Survey age matters
A survey you got a few years ago may not be accepted. Many of the checklists above want a survey from within the last six months; Burnaby's R1 additions checklist says 12 months. If your survey is older than that, talk to your surveyor about an update before you submit.
Common mistakes
Designing from an old plot plan or tax map. They aren't surveys, and they don't show the legal boundary.
Assuming the fence is the property line. Often it isn't. Only a BC Land Surveyor can tell you where the line is.
Changing grades without surveyed existing grades. Height is calculated from grades, so guessing can cost you.
Forgetting what's on title. Easements and rights-of-way can limit where you build. A title search shows what's registered, and some municipalities ask for one with the application. Archivolt can pull one for you.
Ordering the survey after the design. If the survey shows something different from what you assumed, the drawings get redone.
On new builds, missing a foundation-stage survey. In Vancouver, new buildings need one before construction goes past the foundation.
How Archivolt fits in
A typical path looks like this:
You tell us what you want to build.
We check your municipality's current checklist and tell you whether a survey is likely needed and what it should show.
You hire a BC Land Surveyor, and we coordinate with them so the survey covers what the drawings and the checklist need.
We use the sealed survey as the base for the site plan, setback and height checks, and the permit drawings.
We put the application together and deal with the municipality.
Approval is up to your municipality. For boundary questions, the surveyor is the right person.
FAQ
Does every renovation need a survey? No. Interior-only work often doesn't. Additions, foundation work, raising a house, grade changes and new buildings are where it usually comes up.
Can Archivolt do my survey? No. We're a permits and drafting company. We work with your BC Land Surveyor and use their survey in our drawings.
Can I reuse an old survey? Maybe not. Many municipalities want one from the last six months; Burnaby's R1 additions checklist says 12 months. Confirm with yours.
How much does a survey cost? Ask a few BC Land Surveyors for quotes. It depends on the property and what the municipality needs shown.
Is my fence on the property line? Not necessarily. Only a BC Land Surveyor can confirm that.
Planning an addition or renovation?
If you're not sure whether your project needs a survey, start with a call. Archivolt is a permits and drafting company. We help homeowners and contractors across the Lower Mainland with permit drawings, permit applications, title searches and municipal liaison.