What's a Development Permit, and Why Do I Need One? A Lower Mainland Guide

Architectural floor plan drawings spread out on a table

You've got plans for your property. Maybe it's a new house, an addition, a duplex or a small commercial job. Then your municipality tells you that you need a development permit first. What is that, and how is it different from a building permit? Here's a plain guide for the Lower Mainland.

Requirements vary by municipality; confirm with yours.

First: how Archivolt helps

Archivolt is a permits and drafting company serving homeowners, contractors and businesses across the Lower Mainland. For development permits, we check zoning and development permit area maps, order title searches, prepare drawings and site plans, write responses to the design guidelines, put the application package together, coordinate with the other consultants your project needs, and track the application with your local government.

What is a development permit?

In most of BC, development permits come from the Local Government Act, Part 14, Division 7 (read it on BC Laws). A municipality's Official Community Plan (OCP) can mark parts of the community as development permit areas. Under section 489, if your property is inside one of those areas, you generally can't subdivide, or start building, adding to or altering a building, until a development permit is issued, unless your work is exempt. In some areas, even altering the land itself (for example clearing or grading) needs a permit first. That includes environmental and hazard areas, and areas set up for revitalization or for energy, water or greenhouse gas goals.

In plain terms, a development permit is your local government's approval of how a project fits its guidelines for that area. Depending on the area, that can cover the look and layout of a building, landscaping, protecting streams and natural areas, or keeping buildings safe from hazards like steep slopes, flooding or wildfire.

The City of Vancouver works a bit differently. It runs under the Vancouver Charter and its own Zoning and Development By-law, not Part 14 of the Local Government Act. Vancouver's development permit page defines development broadly, including any change in the use of land or a building and the carrying out of construction.

Development permit vs building permit vs variance permit

These three get mixed up a lot.

  • Development permit: your local government's land-use, design, environmental or hazard approval, checked against the guidelines for that development permit area.

  • Building permit: checks the construction itself against the building code. In most municipalities that's the BC Building Code plus the local building bylaw. The City of Vancouver uses its own Vancouver Building By-law instead.

  • Development variance permit: under section 498 of the Local Government Act, it varies a bylaw rule, such as a setback or height, for your property. It's a different permit from a development permit, although under section 490 a development permit itself can also vary some bylaw rules. Vancouver doesn't use this permit. It has its own process for relaxations under the Vancouver Charter.

One doesn't replace another. Having a development permit doesn't mean you have a building permit, and the other way around.

One more limit worth knowing: under section 490(3), a development permit generally can't change the permitted use or density of your land, and under section 498(2) a variance permit can't either. There's a narrow exception under section 491(3) for hazard areas, where permit conditions tied to health, safety or protecting property can limit use or density. If you want more units or a use than your zoning allows, that's a zoning question, not a development permit question. And even when your zoning already allows the project, you may still need a development permit and a building permit.

What kinds of development permit areas are there?

Section 488(1) lists the purposes a municipality can use. Grouped simply:

  • Natural environment: protecting ecosystems, streams and biodiversity

  • Hazards: protection from things like flooding, steep slopes or wildfire

  • Farming: protecting farmland

  • Form and character: the design of intensive residential, commercial, industrial or multi-family buildings, and revitalizing commercial areas

  • Energy, water and greenhouse gases: conservation and emission reduction

  • Resort regions

  • Tenant protection: reducing the displacement of renters when buildings are redeveloped

Each municipality picks which of these it uses, draws them on its maps and sets its own guidelines and exemptions. One property can sit in more than one area at once.

Heritage isn't on that list. Heritage conservation areas come under Part 15 of the Act and use a heritage alteration permit, which is a separate thing. A property protected by its own heritage designation bylaw also needs a heritage alteration permit for many changes, even outside a heritage conservation area (section 611(3)).

When you're likely to need one: some Lower Mainland examples

These are general examples only. Always check your own property with your municipality.

  • District of West Vancouver: has five main area types: Environmental, Wildfire Hazard, Foreshore, Form and Character (for multi-family and commercial areas), and Duplex. The District notes that a development permit can't be used to change permitted land uses or density.

  • District of North Vancouver: has development permit areas that include environmental and hazard areas such as creek, slope and wildfire hazard. For its environmental and hazard areas, the District says a building permit application won't be accepted until the development permit has been approved or an exemption granted.

  • City of Surrey: its development permit areas page describes a Form and Character area covering commercial, industrial and multi-family development across the municipality, with some exemptions (Campbell Heights, for example), and other areas for hazard lands (steep slopes and flood-prone land), sensitive ecosystems and farm protection. Surrey has a new OCP, so check it for your property.

  • City of Burnaby: has areas for Form and Character, Streamside Protection and Enhancement, and Tenant Protection (for redeveloping purpose-built rental buildings with 5 or more units). Burnaby now asks for an Initial Application before most development permit applications, and development permits are generally not needed on lots zoned for small-scale multi-unit housing (R1) unless the streamside rules apply.

  • City of Vancouver: for larger projects, zoning relaxations or certain uses, a separate development permit is needed before you can apply for a building permit. New houses, duplexes and laneway houses go through one combined development/building permit.

The City of North Vancouver, Richmond, Coquitlam and other municipalities have their own development permit areas too. Check their OCP maps or ask their planning department.

How do I know if my property is in a development permit area?

Look at your municipality's OCP maps or its online property viewer, or ask its planning department. Even if your work looks exempt, some municipalities want a formal exemption in writing. Don't assume small or interior-only work is automatically exempt. In the District of North Vancouver's slope hazard areas, for example, any work gets reviewed, and either a permit or a formal exemption is issued.

How the process usually goes

Wood-frame house under construction behind a temporary site fence

The names and order vary, but the steps often look like this:

  1. Check zoning and the development permit area maps for your property.

  2. Pre-application inquiry. Many municipalities offer an early meeting or inquiry with planning staff.

  3. Title search. Many applications ask for a current title search, and the title shows covenants and other notices that can affect your project. Once a development permit is issued, the municipality must file a notice of it on your title (section 503), and the permit's terms bind future owners too. To see what covenants and other registered documents actually say, you may need copies of them, not just the title. Archivolt can order a title search for you.

  4. Complete application. Drawings, site plan, a response to the guidelines and any reports the area calls for.

  5. Staff review and referrals to other departments or agencies.

  6. Public information or advisory review, where your municipality requires it.

  7. Decision by Council or by staff, depending on the municipality and the project.

  8. Permit issued, sometimes with conditions or security. A notice of the permit is filed on your title.

  9. Building permit. Depending on your municipality, it comes after the development permit, or it's combined with it.

How long it takes and what it costs depends on your municipality and your project, so check your municipality's current fees and guidance.

Common mistakes

  • Drawing a full building permit set before checking the development permit area maps

  • Assuming interior or small work is exempt

  • Missing that a lot sits in more than one development permit area

  • Ignoring covenants, conditions or notices already on title

  • Thinking a development permit is the same as a building permit

  • Expecting a development permit to allow more units or a new use

  • Mixing up a development permit with a development variance permit

Who else might you need?

Some development permits need reports or drawings from other professionals. For example, the District of North Vancouver asks for a qualified engineer's or geoscientist's report for slope hazard areas. Environmental areas can call for reports from other qualified professionals, and some applications need a survey from a BC Land Surveyor. Depending on the project, you may also need an architect, a landscape architect or an arborist. We coordinate with them as part of putting your application together.

FAQ

Is a development permit the same as a building permit? No. A development permit deals with land use, design and site issues. A building permit deals with construction.

My job is interior only. Do I need one? Maybe. It depends on the development permit area and its exemptions. Ask your municipality.

Can a development permit let me add units or change the use? Generally no. More units or a different use than your zoning allows is a zoning question. A development permit generally can't vary use or density (there's a narrow exception for hazard conditions).

Does a development permit expire? It can. Under section 504, a permit lapses if construction hasn't substantially started within 2 years of issue, unless the permit says otherwise.

Do the development permit and building permit happen together? It varies. Some municipalities combine them for certain projects, and others need the development permit first.

Do I need an architect or engineer? Sometimes. It depends on the project and the development permit area.

Related reading

Not sure if you need a development permit?

Send us your address and what you're planning. We'll check the zoning and development permit area maps, order a title search if you need one, and talk through what your project may involve. Archivolt helps homeowners and contractors across the Lower Mainland with permit drawings, permit applications, title searches and municipal liaison.