Can You Change Your Plans After the Permit Is Issued and Work Has Started? A Lower Mainland Guide
Updated: Oct 29

You've got the permit, the crew is on site, and now something needs to change. Maybe you want a bigger window, a wall in a different spot, a larger deck, or the contractor wants to do something a different way. Can you just do it? Usually not without telling the municipality first. The good news is that most municipalities have a set process for changing an issued permit. Here's how it works and where Archivolt fits in.
Requirements vary by municipality; confirm with yours.
First: how Archivolt helps
Archivolt is a permits and drafting company. The municipality decides whether to accept a revision, and where a change needs to be sealed, your engineer or other registered professional seals it.
What we do: prepare the revised drawings, put the revision package together and submit it, coordinate with your engineers and other consultants when the change touches their work, and track the revision with the municipality until it's issued.
The short answer: the permit covers the approved drawings
A building permit doesn't let you build anything you want on the property. It covers the work shown on the drawings the municipality accepted. If what you're building changes, the permit usually needs to change with it.
Vancouver spells this out. Per the City's consolidated by-law, the owner has to get the approvals needed before starting the work they relate to, and has to follow the conditions of the permit. It also says no one can do work, or allow work, that goes against the by-law. Other municipalities have their own wording, but the idea is much the same.
So the safe rule is simple: don't build the changed part until the revision is issued.
What counts as a change?
It's not always obvious. Common ones we see questions about:
Moving or removing a wall
Adding, moving or resizing windows and doors
Making a deck, addition or room bigger
Adding a suite or another unit
Structural changes, like a different beam or footing design
The contractor proposing a different way of building something shown on the drawings
Who decides whether a change is minor? The municipality. In Surrey, per its guidance documents, the plan reviewer or inspector decides whether a change is minor enough to show on as-built drawings or needs a revision permit. That's from Surrey's guidance, not its bylaw, and it's still their call. Don't assume a small change is fine in your municipality without asking.
Minor revision, or a whole new permit?
Some changes are too big for a revision. In Vancouver, per the City's consolidated by-law, the Chief Building Official may accept minor revisions to an issued permit, and may require a new permit if the change adds or removes floor area, storeys, dwelling units or major occupancies. "May" is the important word. It's their discretion, not automatic either way.
Burnaby is clearer on one point: adding a principal or secondary suite is a new permit, not a revision.
If your project also has a Development Permit, there's another layer. In Vancouver, building permit plans have to conform substantially with the approved development permit plans, and where the zoning by-law requires it, a Development Permit Amendment is needed. Not every drawing difference means a DP amendment, but it's worth checking before you change anything on the outside of the building.
How a revision usually works
The names change from place to place. Vancouver calls it an amendment or revision, Burnaby an Issued Building Permit Revision, Surrey a revision permit, and Richmond a Design Modification. The steps are often similar:
Revised drawings are prepared with the changes clouded or bubbled, numbered and dated.
A revision form goes in with the drawings.
If the original drawings were sealed by a professional, the revised ones often need to be sealed too.
The municipality reviews it and charges a revision fee.
The revision is issued, and the updated drawings go on site.
Vancouver's by-law also requires the permit drawings to be available on site, so make sure the crew is working from the current set.
Fees are often hourly. A few examples from 2026 sources:
Vancouver (2026 Schedule of Fees): single detached house or secondary suite, $282 for the first hour plus $282 for each extra hour; any other building, $856 plus $427 an hour. Vancouver charges a revision fee on every revision to an issued permit.
Burnaby (2026 fee schedule): $145 an hour, 2-hour minimum, after issuance.
West Vancouver (Fees Bylaw): $150 an hour or part of an hour, after issuance.
New Westminster (fee page): $84.60 an hour, $169 minimum, for revisions to issued drawings.
Other municipalities, including Richmond and the City of North Vancouver, charge revision fees too. Check the current amount with yours.
Can work keep going while the revision is in review?
There's no single answer. Some municipalities let unaffected work and inspections carry on, and some don't. Surrey's house permit page says inspections can't be done while you're waiting for approvals on your revisions. In Burnaby, on Certified Professional projects, the affected work isn't allowed to proceed until the revision is issued.
What to do: don't build the changed part until the revision is issued, and ask your inspector or plan reviewer whether the rest of the work and inspections can continue.
Engineers and other professionals
If an engineer or other registered professional is on the project, changes in their area need to go through them. They usually do field reviews and sign letters at the end saying the work matches their design. If the work on site doesn't match what they designed, that can hold up their sign-off, which can hold up your final. Talk to them before the change, not after.
A change can also bring in a professional who wasn't needed before. That depends on the specific change, so ask early.
What can go wrong if you skip the revision
None of these are automatic. It's up to the municipality, case by case. But in Vancouver, per the City's consolidated by-law, the building official can:
Order work to stop. A stop work order also suspends the permit.
Revoke the permit in certain cases.
Order construction that doesn't comply to be removed.
Require work that was covered before inspection to be uncovered at the owner's expense.
Other things that can happen: inspections get held up, and your final or occupancy gets delayed. Unapproved changes can also cause problems later with insurance or a sale, so ask your insurer or lawyer if that's a worry.
One more thing: filing a revision doesn't extend your permit. In Vancouver, per the City's consolidated by-law, a permit can expire if, in the Chief Building Official's opinion, work isn't started within 6 months, isn't carried out continuously, or stops for 6 months. Keep that in mind if a revision is going to slow the job down.
A simple checklist
Stop and ask before building the changed part.
Ask your municipality whether other work and inspections can continue.
Get the change drawn up properly, and loop in your engineer if it's in their scope.
Submit the revision.
Wait for the revision to be issued.
Don't cover work before it's inspected.
Keep the current stamped set on site.
Keep an eye on your permit's expiry.
FAQ
Can I make a small change without telling anyone? Don't count on it. Even in Surrey, where some minor changes can go on as-built drawings, the reviewer or inspector decides.
Will my whole job have to stop? Not necessarily, and not necessarily not. It depends on the municipality and the project. Ask your inspector.
Does a revision give me more time on my permit? No. Filing a revision doesn't extend the permit.
How long does a revision take? It depends on the municipality and the change. Ask yours.
Need to change your plans?
If something on your job needs to change, call before you build it. Archivolt is a permits and drafting company. We help homeowners and contractors across the Lower Mainland with permit drawings, permit applications, revisions, title searches and municipal liaison.